Roadmap & phases

Eight phases from discovery to launch and beyond, with acceptance criteria.

1 min read Updated 3 Nov 2026 ForAdmin · Head coachTechnical owner
PhaseContentIndicative duration
0 — Discovery and designSign off this documentation, UX/UI, coach identity, database design2–3 weeks
1 — Core (web MVP)Landing page, sign-up and sign-in, questionnaire, admin requests, plans, subscription and payment, admin dashboard, basic notifications6–8 weeks
2 — Content and coachingExercise library, programs, nutrition, measurements and photos, trainee dashboard, coach notes, basic reports6–8 weeks
3 — Communication and integrationChat, Google Meet, full notifications and reminders, Google Sheets4–5 weeks
4 — Intelligence and analyticsAI assistant, advanced reports, activity log, page and video tracking4–5 weeks
5 — Mobile appTrainee + coach apps, push, offline, store publishing8–10 weeks (starts alongside phase 3)
6 — LaunchTesting, security, performance, client training, soft launch then public launch2–3 weeks
7 — LaterAuto-renewal, Tamara/Tabby, challenges and points, blog, wearables, multi-coachBy priority

Durations are estimates for a small team and are re-baselined after design sign-off and team size are confirmed.

General acceptance criteria

  • Every journey in The trainee journey works end to end on web and mobile.
  • Every notification in the table arrives through the specified channel at the specified time.
  • No user can see another user's data (automated permission tests).
  • Admin reports match the real numbers (reconciliation tests).
  • A published plan edit creates a version; a refund creates a credit note; a retried webhook never duplicates a payment.
  • Arabic RTL and English LTR both work on mobile and desktop sizes.

    Change management

    Any addition after sign-off is logged as a change request with: the requirement, the reason, affected screens, database and API impact, security impact, time and cost estimate, and an acceptance criterion. Items marked “later” are not included in the baseline price or timeline.